A 20MW site in violation of their interconnection agreement looked to Affinity Energy to correct ramping behavior and remove oscillation in curtailed output.

Background

A large national utility built a 20MW solar site in Lancaster County, California that went online in early 2016. As part of the interconnection agreement, CAISO (California ISO) regulations require ramping of site output in response to curtailment requests at the industry standard of 10% per minute.

What Our Clients Say About Us

AE_Icon_Quote

Unfortunately, our previous partner didn’t seem to have a strong interest in resolving their issue that ultimately put our project at risk. I knew Affinity Energy’s engineers had a history of solving some challenging analytics and operational issues at solar sites. If anyone could figure out how to solve this problem, I figured Affinity Energy could.

Head of Asset Optimization

National Energy Company

Challenge

Ever since the original integrator installed the control system, the site’s ramping has never worked properly.

The reason it’s gone unchecked for so long, is because the site generally runs uncurtailed. It’s only after CAISO dispatch commands them to reduce output do they notice the problem. The original system integrator tried to fix the problem multiple times, with no success.

As per CAISO regulations, the 20MW site should ramp approximately 2MW per minute. It should follow closely below the commanded curtailment rate as it ramps down, and stick to (not over) that line as it ramps back up.

Instead of following a slow ramp down to a new setpoint, (as shown in Figure 1) the site’s output remained at 20MW for nearly a minute. Then it started loosely following the ramping profile, sporadically jumping across the line nearly a dozen times. Even after the site’s commanded setpoint was steady, site output continued to oscillate above and below the setpoint.

FIGURE 1: This graph shows a test of the site’s ramp response rate before Affinity Energy became involved. The purple line shows the site’s commanded output change from 20MW to 14.2MW. The red line shows what the site should have done to follow dispatch’s command. The blue line shows the site’s actual behavior.

Not only did this site’s ramp response rate occur each time there was a commanded setpoint change, it rendered the site in breach of its interconnection agreement, placing owners at risk of fines or disconnection.

Affinity Energy was brought on at the end of 2017 to troubleshoot and correct the ramping problem.

Solution

Results

As a result of Affinity Energy’s work, the site is now able to achieve ramp rates compliant with CAISO requirements. Oscillation has been eliminated, ramping is consistent with the code, and the site runs at or below its set point booth in steady stand and ramping modes.

FIGURE 2: This graph shows the site’s ramp response rate after Affinity Energy’s rewritten controls code was implemented. The purple line shows the site’s commanded output changes. The red line shows what the site should do to follow dispatch’s command. The blue line shows the site’s actual behavior.