When the Critical Facilities Monitoring System (CFMS) unexpectedly failed for their client, Jones Lang LaSalle turned to Affinity Energy for a quick turnaround to get the system back online.

Jones Lang LaSalle

Jones Lang LaSalle (JLL), is the property manager for one of the world’s leading financial institutions headquartered in Charlotte, NC, and is responsible for managing the CFMS. The CFMS manages all critical equipment for 17 buildings owned by the client in the Charlotte, NC, area. It monitors 113 different device types, including AC units, generators, UPSs, PDUs, transfer switches, switchgear, meters, batteries, and fire alarm panels.

What Our Clients Say About Us

AE_Icon_Quote

Affinity Energy came to our aid without hesitation and as soon as humanly possible. They were flexible enough to work late hours on the weekend, and finished an entire day faster than we anticipated.

Walt Perryman

Operating Engineer at Jones Lang LaSalle

Challenge

In 2015, JLL knew their Critical Facilities Monitoring System (CFMS) needed an upgrade.

The hardware had hit its end of life, some software components were reaching their lifecycle end, and servers were running on an unsupported version of Windows. Unfortunately, JLL failed to secure the budget required for a complete overhaul, and instead started working with Affinity Energy in 2016 to develop an improved disaster recovery strategy. This involved installing a backup virtual machine (VM) host server and using VMWare to run backup VM images in the event of a primary server failure. While not the long-term solution the team had hoped for, it was the best solution given the existing budget constraints.

Midway through the implementation of the backup VM host server, the scope of the project changed when JLL finally received the budget to replace their outdated servers, fibre channel switch, and Storage Area Network (SAN) with a Nutanix, a hyper-converged high availability solution that aims to reduce power and space consumption and eliminate storage complexities.

On December 1, less than a week from the planned installation of the new Nutanix VM host system, the unexpected happened. The existing VM host environment experienced a catastrophic failure. JLL could no longer access the CFMS due to total equipment failure.